Unbuilt PV projects in Japan could have FIT certification withdrawn

Share

Approved PV projects in Japan that are yet to be connected to the grid are being investigated by METI to determine what the delay is – with tough sanctions being considered for those projects found to be stalling deliberately.

METI launched its investigation in late September to ascertain why only one-in-ten PV projects of 400 kW or more have been connected to Japan's grid. Their fact-finding mission is expected to run until October 18, during which time no official announcement from METI will be made, nor will any punitive action be taken.

pv magazine has learned that METI is concerned that some solar developers are deliberately delaying their projects in the hope that module prices will fall, thus delivering improved profit margins. However, METI cannot be sure that this is always the case (delivery times for some equipment varies throughout Japan, so there may well be legitimate reasons why grid connection has been slow), so have commenced an investigation in order to glean accurate first-party feedback, RTS Corporation’s Izumi Kaizuka said by telephone from Tokyo.

"Before December 10, 2012, projects could often be approved without developers securing or fulfilling land lease agreements," said Kaizuka, adding that METI’s investigation will carry out stringent checks to ensure developers can prove land ownership or an agreed land lease.

FIT for punishment

The proposed sanctions for non-compliance with the investigation could include a fine or the cancellation of FIT certification. Kaizuka stressed, however, that METI will follow a seven-step plan before taking any action.

Step one is to ask developers to report the status of their operation. For step two, METI will enquire about each developer's willingness to give up their project without further sanctions.

If the developer refuses to do so, they then must fulfil steps three, four and five: confirm when construction began; provide documents that prove components have been ordered, and provide proof of land purchase/leasing. If steps four and five cannot be satisfied, then the developer has to schedule a date for when these documents can be provided (step six), and provide a valid reason for the delay, such as financing or grid connection negotiations (step seven).

If a developer refuses to comply at any stage, stated Kaizuka, then METI could issue a fine of up to JPY 300,000 (approximately $3,100). METI would not directly force developers to cancel their projects, but they would consider revoking the project’s FIT certification if the developer was thought to be behaving mendaciously.

Kaizuka added that METI believes that while it is possible many PV developers have simply run into financial difficulties or lack the required paperwork to see their projects through to completion, a proportion are in fact deliberately stalling in the hope that module costs will fall further.

The full outcome of the survey is not expected until later this month, after which point METI are likely to issue an official announcement detailing their findings and further – if any – actions.

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Popular content

Daikin launches air-to-water heat pumps for single-family homes

16 December 2024 Daikin has released a line of residential heat pumps, using propane (R290) as the refrigerant, with outdoor unit dimensions of 1,122 mm x 1,330 mm x 6...

Share

Leave a Reply

Please be mindful of our community standards.

Your email address will not be published. Required fields are marked *

By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.

Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.

You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.

Further information on data privacy can be found in our Data Protection Policy.