As part of PV installation efforts, a decision has been made to install PV at the Group’s main overseas manufacturing subsidiaries in Poland and Thailand. NGK CERAMICS POLSKA SP. Z O.O. will install large-scale PV with a total capacity of 15.1 MW on the roof of the buildings and on land at its first factory (Gliwice, Silesia Province), as well as on land neighboring its second factory (Dąbrowa Górnicza, Silesia Province). It is anticipated that these will produce an annual output of 15,240 MWh, which will reduce annual CO2emissions by an estimated 10,000 tons in fiscal 2024, the first full year after the installation. NGK CERAMICS (THAILAND) CO., LTD. (Samutprakarn Province) will install large-scale PV with a total capacity of 4.25 MW on the rooftops of its buildings, which is expected to produce an annual output of 5,560 MWh. Operation is due to start in fiscal 2023 and it will reduce annual CO2 emissions by an estimated 2,630 tons. The Group’s plan is to switch all energy consumed by overseas manufacturing sites to renewable energy by fiscal 2025, including by actively installing PV.
In addition to efforts for reducing CO2emissions currently underway, such as installing PV, acquiring Renewable Energy Certificates (REC), and introducing carbon-neutral city gas, the Group is also launching initiatives including developing technology for manufacturing ceramics using clean energy sources that do not emit CO2, such as hydrogen and ammonia. To achieve net zero CO2 emissions by 2050, NGK will advance various initiatives in regions around the world, including the further installation of PV within the Group and the effective use of renewable energy through storage using NAS® batteries, to contribute to the realization of a carbon neutral society.
PV Installation Roadmap
*Under planning
Figures shown in the table are the PV panel capacity (unit: kilowatts)
1,000 kW = 1MW
NGK CERAMICS POLSKA SP. Z O.O. first factory (scheduled start of PV operation: June 2024)
NGK CERAMICS POLSKA SP. Z O.O. second factory (scheduled start of PV operation: June 2024)
NGK CERAMICS (THAILAND) CO., LTD. (scheduled start of PV operation: July 2023)