Japan's Green Investment Promotion Organization has released the final results of its latest auction for utility-scale solar energy projects.
The state-run agency said that 33.6 MW of PV projects were selected in the procurement exercise. It was Japan's 21st auction for utility-scale solar and was expected to assign 107 MW of generating capacity.
The 22 selected projects range in size from 325 kW to 13.3 MW.
The lowest bid was JPY 5.0 ($0.035)/kWh and was submitted for a 650 kW project. The highest bid of JPY 9.13/kWh was submitted for a 750 kWW project. The average final price came in at JPY 8.08/kWh.
In the last seven auctions, the final average price ranged from JPY 4.5/kWh to JPY 9.73/kWh.
In the 20th round, the Japanese authorities allocated 93 MW of PV with final prices ranging from JPY 4.5 to JPY 8.8/kWh, with the average final price reaching JPY 6.8/kWh.
In the 19th exercise, concluded in March, the Green Investment Promotion Organization allocated 134 MW at an average final price of JPY 5.11/kWh. In the 18th auction, finalized in November 2023, the Japanese authorities allocated 105 MW of PV capacity, with the lowest bid reaching JPY 7.94/kWh. In the 17th exercise, held in late August 2023, the lowest price came in at JPY 8.95/kWh, with 69 MW of allocated capacity.
In the 16th auction held in July 2023, the allocated power was 119.7 MW and the lowest bid came in at JPY 9/kWh. In the 15th solar energy auction, which concluded in March 2023, the Green Investment Promotion Organization only allocated 16.2 MW of the 175 MW tendered. The lowest bid offered in the auction was JPY 9.48/kWh and the average final price was JPY 9.56.
In the 14th exercise, held in November 2022, the Japanese authorities assigned 137.2 MW of PV capacity, out of 175 MW tendered. The lowest bid came in at JPY 9.65/kWh and the average final price was JPY 9.73/kWh.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.
1 comment
By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.
Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.
You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.
Further information on data privacy can be found in our Data Protection Policy.