Troubled solar-wind-storage park finally reaches full potential in Australia

Share

From pv magazine Australia

The Kennedy Energy Park – which includes 15 MW of solar and 43 MW of wind generation, backed by a 2 MW/4 MWh battery energy storage system – is finally operating at full capacity after overcoming grid connection issues.

Japanese renewables company Eurus Energy, which owns the hybrid facility in partnership with Canberra-based developer Windlab, confirmed that the plant near Hughenden, Queensland, has been exporting at 100% capacity since late May.

“Kennedy Energy Park achieved full commercial operations on May 22, 2024,” the company said in a statement.

The Kennedy Energy Park was the first project to combine solar, wind, and battery technologies at scale in Australia’s National Electricity Market when it was completed in late 2018, but its commercial operation has been delayed due to complications with the connection process.

The plant was connected to the grid in 2019 and secured its registration from the Australian Energy Market Operator in mid-2021, but it has taken until now for it to export at 100% capacity.

Windlab has previously said the delay centred around the modeling required to finalize agreement on its generator performance standards.

The commercial operations milestone follows the recent announcement from UK developer Renewable Energy Systems (RES) that it had added the project to its existing Australian asset management portfolio.

The energy park is expected to generate approximately 210,000 MWh of power a year, with Queensland state-owned generator CS Energy to purchase 100% of the output under a 10-year off-take agreement.

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Popular content

SunPower stock crashes 70%
19 July 2024 The company’s share price fell below $1 as it announced it is halting some operations and ending its lease and power purchase agreement offerings, amo...