The Netherlands Authority for Consumers and Markets (ACM) has given the green light to “‘capacity limitation' contracts” for wind and solar power projects.
“Standard contracts ensure that grid operators and producers of sustainable energy can more easily make agreements about congestion management, so that new wind and solar farms gain faster access to the grid,” the ACM said, noting that these contracts have been tested by market and grid operators for two years.
The contracts are a form of congestion management that allows the electricity grid to be used more efficiently. During peak times, grid operators ask solar asset owners to inject less electricity into the grid and, in return, they pay compensation for this form of rush hour avoidance.
However, the ACM said the congestion management contracts are still difficult to implement.
“For example, there is not yet a clear idea of what compensation for flexibility is reasonable,” it explained. “If network operators have to make separate agreements with each new operator about the financial conditions of these contracts, this will take a lot of time.“
The authority said it expects that this issue could be solved if power producers soon use standard contracts with a price formula and capped compensation for temporarily shutting down production.
“By using these standard contracts, producers and grid operators can reach agreements more quickly,” it said.
The contracts can be granted in the Netherlands by congestion service providers (CSPs) acting as intermediaries, in order to make optimal use of the available space on the network.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.
By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.
Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.
You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.
Further information on data privacy can be found in our Data Protection Policy.