KPS Power Generation, a Pacific Energy subsidiary, said it has delivered a “world first” hybrid power station incorporating a 3.5 MW solar PV array and electric turbo compounding (ETC) tech fitted to an existing 10 MW diesel generator at Iluka Resources’ Jacinth-Ambrosia mine site in remote northwestern South Australia.
Pacific Energy Chief Executive Jamie Cullen said the combination of solar PV with ETC technology, which improves the efficiency of diesel generators by recovering waste energy from the exhaust, is like nothing seen before.
“This is an exciting development for both Pacific Energy and Iluka Resources in what we believe is a world first – integrating solar and ETC technology with an existing fossil-fuel facility,” he said.
Juwi Renewable Energy, the Brisbane-based subsidiary of Germany's Juwi, built the renewable energy/diesel hybrid power solution. It incorporates solar PV generation with ETC technology and an upgraded control system. The ETC technology allows the diesel generators to maintain the same power output while using less fuel and producing lower CO2 emissions, The technology has been fitted to each of the existing 10 1 MW generators.
Cullen said the conversion to a hybrid power solution would go a long way to reducing the mine’s electricity demand. The power plant is expected to deliver almost 21% of the mine site’s annual electricity needs.
“The reduction in diesel consumption and improvement in fuel efficiency is expected to save over 2 million litres of diesel and over 5,500 tons of CO2 per year, every year, for at least the next seven years,” he said.
Shane Tilka, general manager for Australian at Iluka Resources, said the shift to a hybrid solution at the Jacinth-Ambrosia operation is exactly what the company needed to do.
“The move from diesel to hybrid energy at Jacinth Ambrosia marks an important evolution in Iluka’s Australian operations. With the large solar resources available to us, the conversion is aligned with Iluka’s purpose to deliver sustainable value,” he said. “The mineral sands and rare earths produced by Iluka are used in a range of sustainable development and renewable energy applications, including solar panels and wind turbines. It is exciting to see our first site powered by the same technology for which the products we mine and process are essential to manufacture.”
KPS, which has operated the 10 MW diesel facility at the Jacinth-Ambrosia mine site since it opened in 2009, will own and operate the hybrid project for an initial term of seven years. The Jacinth-Ambrosia project is Juwi's sixth hybrid project in Australia. It said hybrid solutions have become a focus for its Australian unit.
Juwi is also responsible for Western Australia’s Sandfire DeGrussa Hybrid Project, which features 10.6 MW of PV, a 6 MW battery and a diesel generator. It has been operating since 2016.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.
By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.
Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.
You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.
Further information on data privacy can be found in our Data Protection Policy.