Dutch state-owned electricity transmission system operator Tennet has notified the energy market regulator grid capacity has been reached in the southern and western sections of the Friesland regional network.
Tennet announced today on its website it had formally notified regulator Autoriteit voor Consument en Markt (ACM) that with the region already hosting around 1.5 GW of solar and wind generation capacity, the remaining 980 MW of transmission capacity has been accounted for by signed bids for contracted transmission.
The area affected comprises the 110 kV stations at Gorredijk, Heerenveen, Herbayum, Leeuwarden, Lemmer, Louwsmeer, Marnezijl, Oosterwolde, Oudehaske, Rauwerd, Schenkenschans, Sneek and Wolvega, said the transmission entity.
As a result, Tennet said it expects grid congestion in that section of the network from this year until 2028 and will address the issue with a three to seven-year works program that will include the installation of new transformers and adjustments of the regional high-voltage network.
The Arnhem-based transmission company, which also operates in Germany, said it is looking into the option of applying grid management measures – which can include the option of paying generators to spend periods offline – and will publish the results of that study in the second half of the year.
Tennet said it is already investing €250 million in grid upgrade measures including improving the connection between Oosterwolde and Oudehaske, upgrading capacity at the latter and expanding the Louwsmeer high-voltage substation.
The Ministry of Finance-owned company has been forced to notify such developments on multiple parts of the Dutch network because of the surge in in applications for solar and wind parks in the nation and has considered solutions to the issue such as temporary grid infrastructure and harnessing internet-of-things devices to help shift peak demand periods.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.
By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.
Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.
You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.
Further information on data privacy can be found in our Data Protection Policy.