The Brazilian Ministry of Mines and Energy (MEM) has announced the postponement of national energy generation and transmission auctions. No date was specified for when the auctions would resume amid uncertainty over how long the Covid-19 crisis will persist in the nation.
The ministry stressed on its website the auctions had been postponed rather than cancelled and it hoped they would resume once the public health crisis had abated.
The National Energy Policy Council will evaluate when to resume the exercises. Solar projects were expected to compete in the A-4 and A-6 auctions planned for this year, so named because of the number of years developers have to connect facilities to the grid after signing power supply contracts.
In the A-6 auction held in October, the Brazilian government allocated 2,979 MW of generation capacity of which 530 MW was solar. The final average solar electricity price was BRL84.39/MWh ($16.1028 at today’s exchange rate) and was the lowest among the competing technologies.
In the A-4 auction in late June, the government allocated 211 MW of solar generation capacity and the lowest PV price bid came in at the equivalent of $17.30/MWh by that period’s exchange rate. At the time, that was the lowest electricity price ever recorded for large scale solar in an energy auction.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.
1 comment
By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.
Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.
You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.
Further information on data privacy can be found in our Data Protection Policy.