A ceremony took place last week to celebrate the beginning of the construction of a 17.8 MW PV plant in El Salvador. The Trinidad and Márquez project, being developed by U.S. and Spanish company Real Infrastructure, will be completed within eight months.
The project, within which US$ 50 million will be invested, is divided in two blocks of 8 and 6 MW of capacity, respectively. The vice president of El Salvador Oscar Ortiz and other Salvadorian authorities assisted with the placing of the first module at the ceremony.
The solar plant is specifically located in the municipality of Acajutla and with the initiation of the work it increases the volume of solar currently under construction in El Salvador. The largest PV project currently under construction in the country is the 100 MW Providencia project.
The majority of the Providencia project, as with the Trinidad and Márquez project, was awarded during the first national renewable energy plant tender, which was completed in 2014. During the auction, 94 MW of solar PV was awarded, which is expected to become operational this year.
Furthermore, Real Infrastructure was also one of the winners during the second renewable energy plant tender in El Salvador, which was completed at the beginning of January. Within the second tender, four solar projects, with a combined capacity of 120 MW, and one 50 MW wind project were awarded. According to the National Energy Commission, Real Infrastructure was awarded 10 MW in the last tender.
This article was first published on pv magazine LatAm. It has been translated by Sam Pothecary.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.
By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.
Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.
You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.
Further information on data privacy can be found in our Data Protection Policy.